Project management ch 9 – 6th edition reducing project duration

Reducing Project Duration
Project Management Ch 9
6th Edition

Your Results:
The  answer for each question is indicated by a  .

 

1    
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by:
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts
    

 
2    
Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts
    

 
3    
In a Project Cost-Duration Graph, total project costs are a sum of
    A)
Labor, material and equipment costs
    B)
Direct costs plus interest
    C)
Direct labor costs and the project manager’s salary
    D)
Direct costs and the project manager’s salary
    E)
Direct and indirect costs
    

 
4    
Which of the following is NOT considered a project indirect cost?
    A)
Supervision
    B)
Consultants
    C)
Equipment
    D)
Interest
    E)
The project manager’s salary
    

 
5    
Before crashing, direct costs for an activity represent normal costs, which typically mean low cost, efficient methods for completing the activity in a(n) ________ amount of time.
    A)
Normal
    B)
Budgeted
    C)
Optimized
    D)
Expected
    E)
Targeted
    

 
6    
As a project is crashed and project duration is reduced, direct costs typically
    A)
Increase
    B)
Become unstable
    C)
Decrease
    D)
Become unreliable
    E)
Stay the same
    

 
7    
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
    A)
Normal
    B)
Reserve
    C)
Crash
    D)
Accelerated
    E)
Expedited
    

 
8    
Cost slope can be determined by dividing the
    A)
Run by the rise
    B)
Rise by the run
    C)
Crash cost by the normal cost
    D)
Normal cost by the crash cost
    E)
Indirect cost by direct cost
    

 
9    
In selecting the best activity to crash you would first select the activity with the
    A)
Earliest start time
    B)
Most steep slope
    C)
Least steep slope
    D)
Longest duration
    E)
Largest crash time
    

 
10    
Reducing project duration
    A)
Involves crashing all activities to their crash point
    B)
Can only be done when resources are not constrained
    C)
Is always more expensive
    D)
Tends to increase network sensitivity
    E)
Should be considered for all projects
    

 
11    
The relationship between the normal point and the crash point is assumed to be:
    A)
Linear
    B)
Curvilinear
    C)
Variable
    D)
Conversely related
    E)
Exponentially related
    

 
12    
When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of
    A)
Fast-Tracking
    B)
Using critical-chain project management
    C)
Reducing project scope
    D)
Compromising quality
    E)
Doing it twice- first fast and then ly
    

 
13    
One way of reducing project costs is identifying tasks that _________ can do themselves.
    A)
Vendors
    B)
Suppliers
    C)
Customers
    D)
Company employees
    E)
Project teams
    

 
14    
Which of the following projects would be least beneficial if additional resources were added?
    A)
Splitting and stacking a cord of wood
    B)
Developing new software
    C)
Harvesting a crop by hand
    D)
Building a cabin
    E)
Moving to a new house
    

 
15    
It is going to cost $80,000 a day to simply house and feed a construction crew in the farthest reaches of Northern Alaska. This is an example of reducing project duration due to
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts

 

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

STAY HOME, SAVE LIVES. Order your essay today and save 20% with the discount code ATOM